DAY FOUR - THE 2010 HOME BUILDERS BLITZ
Things are really moving forward at the Blitz Build home in Springville - in fact we are slightly ahead of schedule. The final load of gravel was brought in to finish the crawl space. The drywall subs completed the mud and tape after passing their drywall inspection first thing this morning. The bricklayers started the brick around the front and sides of the home. The stucco guys finished the lathe with an inspection scheduled for tomorrow morning. The gas and water meter were installed. The sprinkler system is working and sod was delivered early afternoon. The finish carpenters arrived at 5:00 p.m. and are scheduled to be done with finish work and doors this evening. Tomorrow the painters will be prepping and priming for paint.