Thursday, September 13, 2012

DAY THREE - THE 2012 HOME BUILDERS BLITZ

All in a days work! It was a crazy busy day at the blitz build site in Payson. Magleby framers finished sheeting the roof and installing the fascia board. Windows and exterior doors were hung. The rough HVAC, electrical, and plumbing were completed. Volunteers from American First Credit Union and others started put up siding on the home The curb was cut and the excavator and flatwork company prepped the garage floor, driveway, and porch to be poured in the morning. Tomorrow the hardworking subs and volunteers will be siding, roofing, insulating, flatwork, and hanging drywall.